Our Mission
“To establish a world-class multimodal cargo aviation hub, linking Asia-Pacific, Europe, and the United States along the New Silk Road, while contributing to the development of aviation sustainability across Kazakhstan, Central Asia, and Eurasia. We are committed to aligning with global ESG principles, ensuring LEED compliance, and reducing our carbon footprint through innovative infrastructure – including the use of SAF and energy-efficient technologies.”
PROJECT DESCRIPTION
GEOPOLITICAL ADVANTAGE
The project is located within a strategically important transport corridor that connects the Asia-Pacific region, Europe, and the United States.
This geographic position provides unique opportunities for the development of a multifunctional aviation cluster, including:
- Cargo and Logistics Hub – operation and handling of transit cargo
- Fuel Hub – technical stopover for refueling international airlines
- Aviation Technical Hub – aircraft maintenance and repair (MRO)
- Aerotropolis – development of commercial and industrial airport infrastructure, including business centers, hotels, coworking spaces, duty-free boutiques, shopping and entertainment centers
Economic Impact
The project is aimed to increase the volume of transit traffic cargo through the “Khorgos – Eastern Gate” hub and to establish a multimodal logistics center by leveraging existing infrastructure potential
Project Timeline
2025–2032
(Three-phase development program)
Airport Infrastructure
- Runway (RWY): 4,650 × 75 m, CAT III
- Aircraft Stands: 10 stands for wide-body aircraft (Class F), 7 stands for Class D aircraft, and 3 stands for helicopters
- Taxiways: 7 taxiways and 1 main taxiway
- Facilities: ATC Tower, Airfield ground lighting system (AGL), Instrument Landing System (ILS), and Automated Weather Observation System (AWOS)
Investment Potential
MODEL AND SUPPORT
Model: BOOT (Build–Own–Operate–Transfer)
Standards: ESG, LEED, SMART AIRPORT 4.0
Support: Government of the Republic of Kazakhstan, Special Economic Zone (SEZ) “Khorgos – Eastern Gate”
OPERATIONAL POTENTIAL
- Cargo Throughput: up to 250,000 tons per year
- Fuel Capacity: over 500,000 tons per year
- Passenger Traffic: up to 2.5 million passengers per year
GEOSTRATEGIC LOCATION
The project is being implemented within the “Khorgos – Eastern Gate” Special Economic Zone (SEZ), covering 840 hectares on the border with China, with the goal of establishing a regional air cargo hub.
INVESTOR INCENTIVES
- 0% tax on land, property, corporate income tax, VAT
- ESG, LEED , SMART AIRPORT 4.0
- Free customs zone
INVESTMENT INDICATORS AND IMPLEMENTATION TIMELINE
Investment Volume:
- Phase I — USD 250 million
- Phase II — USD 150 million
- Phase III — USD 150 million
Construction Phases:
- Phase I: 2025–2027
- Phase II: 2027–2029
- Phase III: 2029–2032
PROJECT PAYBACK INDICATORS
- NPV : KZT 13.3 billion
- IRR: 11.29%
- Payback Period: 11 years
Project Implementation Timeline:
Key Milestones
2023
- October – Memorandum of understanding signed with the management of the SEZ “Khorgos – Eastern Gate”
2024
- March – Memorandum of understanding signed with the Akimat of Zhetysu Region
- March – Kazakh-German joint venture “SKYHANSA” LLP was registered
- May – Land lease agreement signed
- June-October – Pre ingenering design works done
- September – Frame agreement between the Ministry of Transport of Kazakhstan and SKYHANSA signed with participation of German Chancellor and President of Kazakhstan
- October-November – Concept of the General Plan developed
- November – Feasibility study, financial model, and business plan completed
- December – Introductory course on JET A1 aviation fuel and JIG standards conducted for the executives of Kazakhstan airports, Civil Aviation Committee, and Aviation Administration of Kazakhstan
2025
- February – General Plan concept approved by all relevant government bodies and authorities
- June – Expected signing time for the Investment Agreement with the Government of Kazakhstan
- July – Expected SEZ status granting time to the land plot
- July –Land lease agreement extention for 25 years
- September–October – International tender for EPC contractors will be announced
- November–December – Start for the construction of Cargo and passenger airport